All along the watchtower
Let’s take you back to the tail end of 2025 and a project that presented unique challenges for the time of year.
Faced with a tight pre-Christmas deadline and midwinter coastal gales, we successfully completed the installation of the new Littlehampton Harbourmaster’s watchtower in collaboration with Landbuild.
Ground Protection & Logistics
To protect the site’s lawned areas, our hire installs team deployed TUFF TRAK ground protection, ensuring a stable, ‘no-bruise’ platform for all heavy plant and personnel. Due to the structure’s oversized dimensions, the project required specialist abload permits and escort vehicles to navigate the transport route.
Engineering & Lifting Solutions
The timber-clad and copper-roofed watchtower was a fine thing to look at, but it presented unique center-of-gravity challenges, as lifting points had not been integrated into the original design.
Our quick-thinking caps were needed, and the team swiftly engineered a solution:
Custom recovery beams: Fabricated to allow for the extraction of cross-beams from one side of the lift during Phase 1.
The big lift: Using our new 99 t/m FASSI crane to reattach at the exact point of balance for final positioning.
Sequential jacking: We developed a bespoke scheme to jack the pavilion and remove packing shims, ensuring a precision seat onto the tower base.
Despite an 8pm finish and the shortest daylight hours of the year, our team’s resourcefulness ensured the ‘battle’ was won before the holiday break.