Client: Modular Air Systems – Robin Hood School, Sutton

Posted on 16/03/2016

Modular Air Systems had been dropped in it by another hire company at short notice and contacted us looking for a heavy duty solution to spread the load of an 80 tonne crane over a paved area.

Time was of the essence as Traffic Management/Road Closures had been organised and the works installing a large set of modular classrooms was scheduled for a Sunday, beginning install at 06.00 h with a 12 hour work window.

10 off ‘POLYROADS’ with their unique combination of SALLY sockets and 3m x 2m panel sizes allowing to be hauled safely by a 4×4 tow and lightweight flat trailer and deployed with a light weight crane mounted on the clients Ifor Williams trailer, towed by their own Land Rover Discovery.